Group Questions San Onofre’s Decommissioning Fund

Photo by Alison St John

A view of the domes at the San Onofre Nuclear Generating Station north of Oceanside, Oct. 8, 2015.

A nuclear watchdog group says utility companies are underestimating the cost of decommissioning the San Onofre nuclear power plant.

A nuclear watchdog group says utility companies are underestimating the cost of decommissioning the San Onofre nuclear power plant.

The plant’s operator, Southern California Edison, said it has collected enough money — $4.4 billion — to cover those costs, so it has stopped charging rate payers the decommissioning fee that’s been part of their bills since the 1980s.

But attorney John Geesman, of the Alliance for Nuclear Responsibility, has filed a brief with the Public Utilities Commission challenging the “reasonableness” of the decommissioning estimate.

Document

Alliance For Nuclear Responsibility's opening brief

Alliance For Nuclear Responsibility's opening b...

In this brief to the CPUC, the Alliance For Nuclear Responsibility challenges the "reasonableness" of decommissioning cost estimates for the San Onofre nuclear generating station.

Download document

To view PDF files, download Acrobat Reader.

Geesman said Edison’s estimate assumes the federal government will find a permanent storage site for the spent nuclear fuel by 2024, which many say is unlikely. That means the spent nuclear fuel could remain stored on site at San Onofre indefinitely.

Edison’s Tom Palisano, chief nuclear officer at San Onofre, said the federal Department of Energy is responsible for the waste storage after 2024 and the company will sue the DOE for the costs of storage if no permanent off-site location is found.

Photo by Katie Schoolov

The location where Southern California Edison plans to store spent nuclear fuel at the San Onofre Nuclear Generating Station as part of decommissioning, Oct. 8, 2015.

But Geesman said ratepayers will be back on the hook once the $4 billion fund runs out.

“Whether you like it or not, the rate payer is obligated to pay for the cost of this waste storage,” Gesesman said. “Ultimately, you’ve got people paying legacy costs for electricity they never received.”

SDG&E, which owns 20 percent of San Onofre, is still charging San Diego ratepayers customers a decommissioning fee in their monthly bills. But spokeswoman Stephanie Donovan said the utility plans to stop in 2016, once the CPUC approves its decision.

She said SDG&E and Edison have separate decommissioning trust funds, and independently determine whether the money in their funds is adequate.

The amount collected depends on how much electricity a customer uses. For a customer using an average of 500 KWH, that monthly charge is 21 cents, Donovan said.

The $4 billion decommissioning trust fund is separate from the controversial $4.7 billion settlement reached in 2014 by the utility companies after San Onofre was shut down, following a radiation leak in 2012. Under that settlement, ratepayers would foot $3.3 billion of the cost of the premature shutdown, while investors pick up $1.4 billion. Ratepayer advocate groups that signed on to that agreement are now calling for it to be revisited.

FEATURED PODCAST

San Diego News Now podcast branding

San Diego news; when you want it, where you want it. Get local stories on politics, education, health, environment, the border and more. New episodes are ready weekday mornings. Hosted by Anica Colbert and produced by KPBS, San Diego and the Imperial County's NPR and PBS station.

  • Need help keeping up with the news that matters most? Get the day's top news — ranging from local to international — straight to your inbox each weekday morning.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Curious San Diego banner

Want more KPBS news?
Find us on Twitter and Facebook, or sign up for our newsletters.

To view PDF documents, Download Acrobat Reader.